Public Sector
- Client:
- Sydney Trains
- Project Value:
- $600,000
Works required the staged mass excavation of slope with stabilisation measures, Form-Reo-Pour of concrete slab, block wall installation, waterproofing, drainage and handrails. All works were completed within rail corridor outside of possession with trains running.
- Client:
- Sydney Trains
- Project Value:
- $1,900,000
Demolition and reconstruction of existing platform over 3 possession weekends with post possession works. The works involved the demolition and excavation of the existing platform and reinstatement using precast concrete culverts, backfilling, drainage works, and concrete suspended and ground slabs.
- Client:
- Lend Lease
- Project Value:
- $1,300,000
Construction of new concrete footings, ground slab and suspended slabs for new control tower for Department of Defence with Lend Lease as the Managing contractor (No photos allowed due to security).
- Client:
- Sydney Trains
- Project Value:
- $1,600,000
Demolish and reconstruction of existing platform over 3 weekend possessions.
- Client:
- Botany Bay Council
- Project Value:
- $60,000 Plus
Demolition, construction of footings and coloured concrete walls to radius
- Client:
- Railcorp
- Project Value:
- $750,000 Plus
Construction of new drainage and platform slabs during possessions allowing for works around the clock, post possession platform demolition and replacement.
- Client:
- Public Works
- Project Value:
- $250,000
Excavation and sub grade works for new concrete roadway at the prison entrance for Corrective Services through Public Works. This required working in a high security environment.
- Client:
- Lahey Constructions
- Project Value:
- $400,000 Plus
Footings, slabs on ground and suspended, ramps, concrete toppings,exposed aggregate paving,plain concrete pavements and kerbs, floor repairs.
- Client:
- John Holland
- Project Value:
- $2,000,000 Plus
Concrete pavements package including footings, kerbs , pavements and specialised army structures for new army base. Total job area 30,000m
- Client:
- Sydney Trains
- Project Value:
- $2,500,000
Platform reconstruction completed in 3 stages. Work done in railway possession during a 48 hour period. Stage 1 completed on time with a satisfied client.